| EAST
86th STREET AT KEYSTONE AVENUE
ROAD RESURFACING, AUXILIARY LANE
CONSTRUCTION AND SIGNAL INSTALLATION
INDIANAPOLIS, INDIANA
DPW PROJECT NO.: ST-04-062 /INDOT PROJECT NO.: R-24556
As Prime Consultant, VS ENGINEERING
INC. provided construction inspection services for
the East 86th Street at Keystone Avenue road resurfacing,
auxiliary lane construction and traffic signal installation
project. The project involved adding 1,000 feet turn lanes
for eastbound and westbound East 86th Street, adding new
traffic signals, and widening and resurfacing pavement.
In
addition, three concrete barrier walls between the twin
Keystone Avenue overpass bridges were constructed, straight
and shop curved guardrails were installed, and a six-foot
wide, 900-foot long concrete center curb and two concrete
curb-surrounded sod center islands were constructed. The
street was widened on both sides, which required concrete
pavement removal, concrete pavement patching and asphalt
widening.
VS ENGINEERING INC. provided
the following services for this project: |
|